Satellite Radar Reveals Deceptive Slowdown Before Tragic Tailings Dam Collapse
Researchers tracked millimeter-level shifts at the Tonglüshan tailings dam, uncovering how underground mine collapses and rainfall set the stage for disaster.
A partial breach of the Tonglüshan tailings dam in Hubei Province released roughly 500,000 cubic meters of toxic tailings slurry on March 12, 2017, following a prolonged period of hidden structural shifts. Researchers recently investigated what happened before the disaster by combining satellite radar observations with an improved displacement analysis technique, uncovering a deceptive slowdown in ground movement right before the collapse.
The study, published in PLOS One, was conducted by Qiao Liang and colleagues from China, who analyzed radar data collected by the Sentinel-1 satellite between April 2015 and March 2017. Tailings dams store mining waste as a mixture of fine rock particles and water behind engineered embankments. Globally, thousands of such facilities store billions of cubic meters of waste, and more than ninety percent of severe dam failures since 1950 have occurred in dams operating at or below their designed capacity.
How Can Satellite Radar Track Dam Movement from Space?
The research team employed a technique called Small Baseline Subset Interferometric Synthetic Aperture Radar, known as SBAS-InSAR. This satellite method compares radar signals reflected from the ground across multiple passes to measure millimeter-level surface displacements over time. Because raw radar records contain noise from atmospheric delays and signal distortions, the team developed an improved displacement tangent-angle method to categorize movement into distinct phases.

By applying a three-point moving-average smoothing window chosen through a quantitative bias-variance trade-off, the researchers successfully filtered out high-frequency noise without erasing critical pre-failure acceleration signals. This analytical approach divided the deformation history of representative dam monitoring point B3 into four distinct stages: initial deformation, constant-rate movement, accelerated deformation, and a post-accelerated transitional state.
Why Did the Dam Collapse Years After Mining Stopped?
The satellite data revealed two distinct deformation zones, designated M1 and M2, across the northern section of the dam. Zone M1 experienced significant movement driven by the underground collapse of abandoned mine goafs, which are underground cavities left behind by previous extraction. Progressive roof caving in these subterranean voids caused differential foundation settlement, creating a concentric subsidence bowl centered at monitoring point B3.
As the foundation settled, tensile stresses tore through the overlying loose tailings material, generating visible cracks up to twenty centimeters wide. Heavy seasonal precipitation subsequently infiltrated these openings, elevating pore water pressure and drastically reducing the shear strength of the soil. Pearson correlation analysis showed that the statistical relationship between daily rainfall and the dam deformation rate jumped to an extremely strong level after the cracks formed, confirming that rainwater acted as a major catalyst by lubricating the internal structure.

What Does a Decreasing Deformation Rate Mean for Safety?
One of the most counterintuitive findings involves the fourth deformation stage, where the average displacement rate at point B3 dropped from 1.53 millimeters per twelve days down to 0.68 millimeters. Rather than indicating that the dam was stabilizing, this deceleration marked a temporary mechanical equilibrium caused by reduced rainfall and the partial closure of shifting cracks.
The authors emphasize that this low-rate phase represents a critical window of vulnerability rather than recovery. Because irreversible structural damage had already accumulated internally, the temporary restoration of soil strength masked the approach of imminent failure. When heavy pressures eventually overwhelmed the remaining resistance, the dam ruptured suddenly, resulting in two fatalities, one missing person, and widespread ecological contamination across local farmland and water systems.
The research was published in PLOS One on November 25, 2026.
This article has been fact checked for accuracy, with information verified against reputable sources. Learn more about us and our editorial process.
Last reviewed on .
Article history
- Latest version
Reference(s)
- Liang, Qiao., et al. “Displacement stage division and characteristic analysis before failure of Tonglüshan tailings dam based on improved displacement tangent angle method.” PLOS One, vol. 21, no. 11, November 25, 2026, pp. e0363796 Public Library of Science (PLoS), doi: 10.1371/journal.pone.0363796. <https://doi.org/10.1371/journal.pone.0363796>.
Cite this page:
- Posted by Deepak Malhotra